Large solar and energy storage projects are typically defined as those 10 megawatts or larger. These projects interconnect with the transmission grid and the project owners sell power directly to the electric grid after being approved by the Electric Reliability Council of Texas (ERCOT).
Note: BEC does not have any oversight or approval authority associated with these projects. ERCOT and the Public Utility Commission of Texas have the oversight and approval authority.
Once the projects are approved by ERCOT, the project owner is now a generator of energy and a customer of transmission service to the ERCOT grid. PUCT governs this process. Read the full rules here.
Once a project is sized and the site is selected, it must register with ERCOT.
The planning, design and interconnection of these projects are driven by requirements provided by ERCOT and a process that is outlined by the PUCT.
One of the requirements is that the project owner must also conduct a Full Interconnection Study to analyze the impact on the transmission system, and includes the identification and location of an interconnection point and substation.