Before a site visit is scheduled:

  • Submit an application, provide required documents, and pay engineering fee
  • Determine where you will want the final metering point to be
  • Identify the location of privately owned buried lines and septic facilities when applicable

Site visit:

  • The field staking technician will design the shortest, most feasible route to the desired metering point
  • Notify the technician of concerns such as vegetation clearing
  • Technician will place stakes along the route, collect GPS points, determine the need for easements and/or permits

After the site visit:

  • Technician will complete staking sheets, cost estimate, and any other required documents
  • Office technicians will email or mail the cost estimate, a design approval form, and any other required documents
  • Upon receipt of payment and required documents the work order will be released to construction