Before a site visit is scheduled:
- Submit an application, provide required documents, and pay engineering fee
- Determine where you will want the final metering point to be
- Identify the location of privately owned buried lines and septic facilities when applicable
Site visit:
- The field staking technician will design the shortest, most feasible route to the desired metering point
- Notify the technician of concerns such as vegetation clearing
- Technician will place stakes along the route, collect GPS points, determine the need for easements and/or permits
After the site visit:
- Technician will complete staking sheets, cost estimate, and any other required documents
- Office technicians will email or mail the cost estimate, a design approval form, and any other required documents
- Upon receipt of payment and required documents the work order will be released to construction