|
The Medina Lake to Pipe Creek transmission
line supplies power from the state-wide electricity transmission network for
BEC Members in the Medina Lake area.
The current line was built in 1964 and has
served BEC members well for the past forty years. However, the Medina Lake
area has experienced tremendous growth during those years and has out grown
the line.
Rebuilding
the BEC Transmission Line
BEC must rebuild the line in the
next few years to maintain the reliability and quality of service Members
have come to expect. We will be changing it from a 69 kilo-volt (kV) to a
138 kV line that will be able to move more power. The upgrade requires that
we replace the existing poles and wire.
Most of the spans in the new line will be
supported by a single concrete pole about seventy feet tall. The type of
construction BEC is using will require fewer poles with longer lengths or
spans between them. This means a smaller environmental footprint.
Location of Line
The newly rebuilt line will be in the same
location as the old one, but it will require taller poles and a larger
right-of-way area.
Additional Right-of-Way
Area Needed
The current line is in the middle of
a forty foot right-of-way which means there is twenty feet on either side of
the line. For the newly rebuilt line BEC will need a total of eighty feet
(forty feet on either side of the line). This means we need an additional
forty feet of right-of-way, that is twenty more feet on either side of the
line, bringing the total right-of-way area to eighty feet.
Additional Area Needed
for “Swing Out”
The newly rebuilt Medina Lake to Pipe Creek
transmission line will operate at a higher voltage, will be on taller poles
and will use fewer poles per mile than the existing line. The additional
right-of-way area is needed because the wire on the line will “swing out”
further from the centerline during times of high wind.
This means BEC will not necessarily clear
the additional right-of-way area all the way to ground level. Some trees may
need to be topped out, but they will not be cut down at the trunk.
The line is located in areas where there
are mostly cedar trees. These trees do not usually grow tall enough to
interfere with the new line, even during times of high wind.
What
if BEC can not get the extra right-of -way?
If BEC is not able to
get the additional right-of-way in an area for the new line it will have to
use more poles and shorter spans.
Why
doesn’t BEC put the line underground?
Putting a 138 kV
transmission line underground is extremely expensive. No other BEC
transmission line is underground. It is rare to find a transmission line
anywhere that is buried.
What
precautions will BEC take if it has to trim trees in the new right-of-way
area?
All employees and
contractors that trim trees for BEC use practices consistent with arborist
professionals. They are required to paint fresh cuts and clean equipment
when they are dealing with trees susceptible to Oak Wilt and Live
Oak Decline.
When
will construction start on the line?
Rebuilding the line is
expected to begin in 2010. However, BEC has to get commitments on the
additional right-of-way area now, so that engineering can begin.
What
if I have additional questions?
The BEC website has a
section devoted to the Medina Lake to Pipe Creek Transmission Line Rebuild
project. You may also contact BEC’s project manager, Eddie Rowe,
830-796-6039. |